P00012 RAAF Base Townsville AIR 7000 2B MPAR Sep 2025
Engaged by Fulton Hogan, we continue our relationship with RAAF Townsville upgrading their existing AGL system. This is a major...
AGL Control Cubicle Tests and Checks – Correct system operation, status of components (corrosion, operation), replacing corrosion vapor inhibitors after 2 years, electrical safety tests as per AS3000, testing Automatic Transfer Switch operation for the backup generator

Back up diesel generator – Testing electrical output, testing correct operation and correct response to the control signals from the control system

Pit and Duct – Checking the status/cleaning the pits, greasing the bolt, replacing any damaged bolts (lawnmower), replacing weed mat pit surround

Light fittings – Greasing all the bolts and screws, cleaning lenses, levelling lights, replacing any damaged/nonoperational lights and damaged bolts and screws, testing the correct operation of the lights

Primary cable – Testing continuity and insulation resistance of the primary cable, rectification works to improve the readings, and PAL – Testing correct operation of the PAL and its interface with the control system

Engaged by Fulton Hogan, we continue our relationship with RAAF Townsville upgrading their existing AGL system. This is a major...
Avionics have Joint Ventured this Project with ADB Safegate. Avionics will complete all major AGL infrastructure and on pavement AGL installation. The project...
Avionics engaged by Downer to complete an important overlay upgrade at Mackay Airport. The project includes the removal of existing...
Avionics were engaged by Downer to complete 3 High Mast Lighting positions complete with ewo LED lighting in mid 2025. ...
Engaged in March 2024 by Fulton Hogan, Avionics were preferred to complete all the AGL Infrastructure and on pavement cannister...
The Department of Defence (DoD) National Airfield Works Program is a 10-year rolling Airfield Capital Works maintenance program which encompasses...
Taxilane DOM2 and Taxilane DOM 3 are critical pavements servicing many of the Domestic Terminal aircraft parking aprons. These pavements...
The scope of this project includes all works associated with the temporary removal and reinstallation, of the existing AGL as...
The existing runway and taxiway surfaces have been servicing Adelaide Airport since 2010/2011 and are now due for maintenance to...
Avionics supply a wide range of Quality Aeronautical Ground Lighting Components from reputable high end companies including: